Learning Objective 04-P3: Allocate overhead costs using activity-based costing.
In activity-based costing, the costs of related activities are collected and then pooled in some logical manner into activity cost pools. After all activity costs have been accumulated in an activity cost pool account, cost objects are assigned a portion of the total activity cost using a cost driver (allocation base).
Knowledge Check 01
In step _____ in activity-based costing, overhead costs are allocated to cost objects.
multiple choice
one
two
three Correct
Explanation
Knowledge Check 01
The third step is to allocate overhead costs to cost objects.
An activity cost driver is a factor that causes:
multiple choice
an activity to go up or down.
the cost of an activity to go up or down. Correct
company’s overall costs to go up or down.
group of costs that are related to the same activity to go up or down.
Explanation
Knowledge Check 01
An activity cost pool is a group of costs that are related to the same activity. An activity cost driver is a factor that causes the cost of an activity to go up or down.
Step 2 of ABC costing is to:
multiple choice
identify activities and their budgeted overhead cost.
compute activity overhead rate for each activity. Correct
allocate overhead cost to cost objects.
Explanation
Knowledge Check 01
Step 1 is identify activities and their budgeted overhead cost. Step 2 is to compute activity overhead rate for each activity. Step 3 is to allocate overhead cost to cost objects.
In step 3 of ABC, overhead cost is allocated to activities based on the following formula:
multiple choice
actual activity usage divided by activity rate
actual activity usage times activity rate
budgeted activity usage divided by budgeted activity rate
actual activity usage times budgeted activity rate Correct
Explanation
Knowledge Check 01
Step 3 allocates overhead costs to cost objects based on the following formula: actual activity usage times the activity rate.
The plantwide rate method, compared to activity-based costing can _____.
multiple choice
Overcost low-volume complex products
Undercost low-volume complex products Correct
Will always lead to the best product pricing decision
Explanation
Knowledge Check 01
A single plantwide rate does not capture the products’ different use of these activities and often distorts product costs. With the plantwide rate method, low-volume complex products are undercosted, and high-volume simpler products are overcosted. Using the plantwide rate method sometimes can lead to bad product pricing and product mix decisions.
Thanks
No comments:
Post a Comment