Activity
|
Time (weeks)
|
Immediate Predecessor(s)
|
Activity
|
Time (weeks)
|
Immediate Predecessor(s)
|
A
|
7
|
minus
|
E
|
4
|
B
|
B
|
8
|
minus
|
F
|
7
|
B
|
C
|
3
|
A
|
G
|
10
|
C, E
|
D
|
2
|
A
|
H
|
8
|
D , F
|
Dave's earliest start (ES) and earliest finish (EF) are:
Activity
|
ES
|
EF
|
A
|
0
|
7
|
B
|
0
|
8
|
C
|
7
|
10
|
D
|
7
|
9
|
E
|
8
|
12
|
F
|
8
|
15
|
G
|
12
|
22
|
H
|
15
|
23
|
Dave's latest start (LS) and latest finish (LF) are:
Activity
|
LS
|
LF
|
H
|
15
|
23
|
G
|
13
|
23
|
F
|
8
|
15
|
E
|
9
|
13
|
D
|
13
|
15
|
C
|
10
|
13
|
B
|
0
|
8
|
A
|
3
|
10
|
The slack times are:
Activity
|
Slack
|
A
|
3
|
B
|
0
|
C
|
3
|
D
|
6
|
E
|
1
|
F
|
0
|
G
|
1
|
H
|
0
|
The activities on the critical path are
.
B - F - H
The total project completion time for Dave =
23
weeks.