Sunday 8 April 2018

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine​ ES, EF,​ LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity​ times:

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
Dave's earliest start (ES) and earliest finish (EF) are:
Dave's latest start (LS) and latest finish (LF) are:
The slack times are:
The activities on the critical path are
B - F - H
.
The total project completion time for Dave =
23
weeks.

here

No comments:

Post a Comment