Task time estimates for the modification of an assembly line at Jim​ Goodale's Carbondale,​ Illinois, factory are as​ follows:

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

For path
Upper B minus Upper E minus Upper G ,
the duration is
16.3
hours ​(round your response to one decimal​ place).
For path
Upper A minus Upper C minus Upper E minus Upper G ,
the duration is
20.1
hours ​(round your response to one decimal​ place).
For path
Upper A minus Upper C minus Upper D minus Upper F minus Upper G ,
the duration is
31.4
hours ​(round your response to one decimal​ place).
For path
Upper B minus Upper D minus Upper F minus Upper G ,
the duration is
27.6
hours ​(round your response to one decimal​ place).
The critical path is the path that has the longest time path. The critical activities for the leadership training program development project are
.

The project length for the leadership training program development project​ =
31.4
hours ​(round your response to one decimal​ place).