Task time estimates for the modification of an assembly line at Jim​ Goodale's Carbondale,​ Illinois, factory are as​ follows:

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

For path
Upper B minus Upper E minus Upper G ,
the duration is
16.3
hours (round your response to one decimal place).
For path
Upper A minus Upper C minus Upper E minus Upper G ,
the duration is
20.1
hours (round your response to one decimal place).
For path
Upper A minus Upper C minus Upper D minus Upper F minus Upper G ,
the duration is
31.4
hours (round your response to one decimal place).
For path
Upper B minus Upper D minus Upper F minus Upper G ,
the duration is
27.6
hours (round your response to one decimal place).
The critical path is the path that has the longest time path. The critical activities for the leadership training program development project are
.

The project length for the leadership training program development project =
31.4
hours (round your response to one decimal place).