Tuesday, 3 April 2018

Which of the following is the calculation to compute the standard cost of direct labor?

Which of the following is the calculation to compute the standard cost of direct labor?
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
Standard Quantity of Direct Labor × Standard Price of Direct Labor
·         
YOU WERE SURE AND INCORRECT
Total estimated variable Manufacturing Overhead / Total estimated amount of the allocation base
·         
Standard Quantity of Machine Hours × Variable Manufacturing Overhead Rate
·         
Standard Quantity of Direct Materials × Standard Price of Direct Materials
·         
I DON'T KNOW YET

Pool Manufacturing manufactures parts for one type of pool. The managerial accountant provided the following data for March:

Pool Manufacturing
Manufacturing Report for March
Number of parts produced
35,000 parts
Standard variable manufacturing overhead rate
$30 per machine hour
Standard hours required per part
0.20 machine hours
Actual machine hours
3,250 machine hours
Actual variable manufacturing overhead costs
$92,000

What is the variable manufacturing overhead efficiency variance in March?
ANSWER
INCORRECT
·         
$112,500 U
·         
THE CORRECT ANSWER
$112,500 F
·         
YOU WERE SURE AND INCORRECT
$11,250 F
·         
$11,250 U
·         
I DON'T KNOW YET

The variable overhead rate variance ________ .
ANSWER
INCORRECT
·         
is directly tied to the efficiency with which the machine hours are used
·         
is NOT known as the variable overhead spending variance
·         
YOU WERE SURE AND INCORRECT
is the difference between the actual machine hours run and the standard machine hours allowed for the actual volume, computed at the variable manufacturing overhead rate
·         
THE CORRECT ANSWER
is the difference between the actual variable manufacturing overhead costs incurred during the period and the amount of variable manufacturing overhead expected, considering the number of actual hours worked
·         
I DON'T KNOW YET

The variable overhead rate variance is the difference between the actual variable manufacturing overhead costs incurred during the period and the amount of variable manufacturing overhead expected, considering the number of actual hours worked is true.

The variable overhead efficiency variance is the difference between the actual machine hours run and the standard machine hours allowed for the actual volume, computed at the variable manufacturing overhead rate.

The variable overhead efficiency variance is directly tied to the efficiency with which the machine hours are used instead of the variable overhead rate variance.

The variable overhead rate variance is known as the variable overhead spending variance.

Terry’s Tree Service produces parts for saws. The managerial accountant reported the labor data as outlined below. What is the direct labor rate variance for the period?

Terry’s Tree Service
Labor Report
Actual direct labor hours used
38,000
Actual rate per hour
$15.00
Standard rate per hour
$15.05
Standard hours for units produced
34,500

ANSWER
INCORRECT
·         
$190 U
·         
THE CORRECT ANSWER
$1,900 F
·         
YOU WERE SURE AND INCORRECT
$1,900 U
·         
$190 F
·         
I DON'T KNOW YET

The direct labor rate variance is $1,900 F.

Direct Labor Rate Variance = (Actual Rate per Hour – Standard Rate per Hour) × Actual Hours
($15.00 - $15.05) × 38,000 = $0.05 × 38,000 = $1,900 F
The analysis shows the overall dollar impact of paying an average wage rate that was lower than anticipated. Therefore, the direct labor rate variance was favorable. The other answers are not correct.

The ________ measures the difference between the actual fixed overhead costs incurred and the budgeted fixed overhead costs.
ANSWER
INCORRECT
·         
fixed overhead volume variance
·         
standard fixed overhead cost allocated to production
·         
YOU WERE SURE AND INCORRECT
fixed overhead volume variance
·         
THE CORRECT ANSWER
fixed overhead budget variance
·         
I DON'T KNOW YET

The fixed overhead budget variance measures the difference between the actual fixed overhead costs incurred and the budgeted fixed overhead costs.

The fixed overhead volume variance is the difference between the budgeted fixed overhead and the standard fixed overhead cost allocated to production.

The standard fixed overhead cost allocated to production is the standard hours allowed multiplied by the standard rate.

The fixed overhead volume variance is the difference between budgeted fixed overhead and standard fixed overhead cost allocated to production.


Pool Manufacturing provided the following manufacturing report from January. What is Pool Manufacturing’s fixed overhead volume variance in January?

Pool Manufacturing
Manufacturing Report for January
Number of parts produced
50,000 parts
Standard variable manufacturing overhead rate
$33 per machine hour
Standard hours required per part
0.15 machine hours
Actual machine hours
3,450 machine hours
Actual variable manufacturing overhead costs
$100,000
Budgeted fixed overhead
$280,000

ANSWER
INCORRECT
·         
$19,000 U
·         
$16,500 U
·         
THE CORRECT ANSWER
$32,500 U
·         
YOU WERE SURE AND INCORRECT
$18,500 U
·         
I DON'T KNOW YET

Pilot Manufacturing’s fixed overhead volume variance for April is $32,500 U. The other answers are not correct.
Step 1: Compute Standard Fixed Overhead Cost Allocated to Production
= 50,000 parts × .15 machine hours × $33 per hour
= 7,500 machine hrs/part × $33/machine hr = $247,500
Step 2: Fixed Overhead Volume Variance = Budgeted Fixed Overhead – Standard Fixed Overhead Cost Allocated to Production
= $280,000 - $247,500 = $32,500 U


Which of the following is the formula to compute the direct labor efficiency variance?
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
Standard Rate × (Actual Hours – Standard Hours Allowed)
·         
YOU WERE SURE AND INCORRECT
Standard Price × (Actual Quantity Used – Standard Quantity Allowed)
·         
Actual Quantity Purchased × (Actual Price – Standard Price)
·         
Actual Hours × (Actual Rate – Standard Rate)
·         
I DON'T KNOW YET

Standard Rate × (Actual Hours – Standard Hours Allowed) is the formula to compute the direct labor efficiency variance.

Actual Hours × (Actual Rate – Standard Rate) is the formula to compute the direct labor rate variance.

Actual Quantity Purchased × (Actual Price – Standard Price) is the formula to compute the direct material price variance.

Standard Price × (Actual Quantity Used – Standard Quantity Allowed) is the formula to compute the direct material quantity variance.

Which of the following journal entries represents the recording of the sale and release of inventory in a normal system?
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
A debit to Finished Goods Inventory and a credit to Sales Revenue
·         
A debit to Finished Goods Inventory and a credit to Accounts Receivable
·         
YOU WERE SURE AND INCORRECT
A credit to Finished Goods Inventory and a debit to Fixed Manufacturing Overhead
·         
A credit to Finished Goods Inventory and a debit to Sales Revenue
·         
I DON'T KNOW YET
A debit to Finished Goods Inventory and a credit to Sales Revenue represents the recording of the sale and release of inventory in a normal system. The other answers are not correct.
Which of the following is the calculation to compute the predetermined variable manufacturing overhead rate?
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
Total Estimated Variable Manufacturing Overhead / Total estimated amount of the allocation base
·         
Standard Quantity of Machine Hours × Fixed Manufacturing Overhead Rate
·         
YOU WERE SURE AND INCORRECT
Total Estimated Fixed Manufacturing Overhead / Total estimated amount of the allocation base
·         
Standard Quantity of Machine Hours × Variable Manufacturing Overhead rate = Standard Variable Manufacturing Overhead
·         
I DON'T KNOW YET

Total Estimated Variable Manufacturing Overhead / Total estimated amount of the allocation base is the calculation to compute the Variable Manufacturing Overhead rate.

Standard Quantity of MH × Variable Manufacturing Overhead rate = Standard Variable Manufacturing Overhead = Standard cost of variable manufacturing overhead

Total estimated fixed Manufacturing Overhead / Total estimated amount of the allocation base = Fixed Manufacturing Overhead rate

Standard Quantity of Machine Hours × Fixed M Manufacturing Overhead rate = Standard Fixed Manufacturing Overhead


Marshall’s Toy Shop produces and sells small dolls for children. During the production process, the employees use six pounds of plastic for each doll, including an allowance for normal amounts of spoilage and waste. The manager can purchase the plastic for $3 per pound.
What is the standard cost of plastic per pound for each doll?
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
$18.00
·         
$.18
·         
YOU WERE SURE AND INCORRECT
$1.08
·         
$1.80
·         
I DON'T KNOW YET

The standard cost of plastic per pound for each doll is $18.00 /lb. The other answers are not correct.
6 lbs. × $3/lb = $18.00


Pilot Manufacturing prepared a report and noted budgeted fixed overhead costs of $3.75 per unit at 1,400 units. In November, the managerial accountant incurred actual fixed overhead costs of $4,200 and the actual production was 1,400 units.
What is Pilot Manufacturing’s fixed overhead budget variance for November?
ANSWER
INCORRECT
·         
$1,050 U
·         
THE CORRECT ANSWER
$1,050 F
·         
YOU WERE SURE AND INCORRECT
$10,500 U
·         
$10,500 F
·         
I DON'T KNOW YET

The fixed overhead budget variance for October is $1,050 F. The other answers are not correct.
Fixed Manufacturing Overhead Budget Variance =Actual Fixed Overhead Costs – Budgeted Fixed Overhead Costs
= $4,200 – ($3.75 × 1,400)
= $4,200 - $5,250 = $1,050 F
The variance is favorable because the actual costs are lower than budgeted.


Marshall’s Upholstery produces buttons for couches. The managerial accountant reported the labor data as outlined below. What is the direct labor rate variance during January?

Marshall’s Upholstery
Labor Report
Actual direct labor hours used
36,000
Actual rate per hour
$19.00
Standard rate per hour
$16.75
Standard hours for units produced
35,500

ANSWER
INCORRECT
·         
$8,100 U
·         
THE CORRECT ANSWER
$81,000 U
·         
YOU WERE SURE AND INCORRECT
$8,100 F
·         
$81,000 F
·         
I DON'T KNOW YET

The direct labor rate variance is $81,000 U.

Direct Labor Rate Variance = (Actual Rate per Hour – Standard Rate per Hour) × Actual Hours ($19.00 - $16.75) × 36,000 = ($2.25 × 36,000) = $81,000 U
The overall dollar impact of paying an average wage rate that was higher than planned means that this is an unfavorable result. The other answers are not correct.


Actual Hours × (Actual Rate – Standard Rate) is the formula to compute ________
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
variable manufacturing overhead rate variance
·         
fixed overhead volume variance
·         
YOU WERE SURE AND INCORRECT
fixed overhead budget variance
·         
variable manufacturing overhead efficiency variance
·         
I DON'T KNOW YET

Actual Hours × (Actual Rate – Standard Rate) is the formula to compute the variable manufacturing overhead rate variance.

Variable Manufacturing Overhead Efficiency Variance = Standard Rate × (Actual Hours – Standard Hours Allowed)

Fixed Overhead Budget Variance = Actual Fixed Overhead – Budgeted Fixed Overhead

Fixed Overhead Volume Variance = Budgeted Fixed Overhead - Standard Fixed Overhead Cost Allocated to Production = Budgeted Fixed Overhead – (Standard Hours × Standard Rate)


Which of the following is the calculation to compute the standard cost of direct materials?
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
Standard Quantity of Direct Materials × Standard Price of Direct Materials
·         
YOU WERE SURE AND INCORRECT
Standard Quantity of Direct Labor × Standard Price of Direct Labor
·         
Total estimated variable Manufacturing Overhead / Total estimated amount of the allocation base
·         
Standard Quantity of Machine Hours × Variable Manufacturing Overhead rate
·         
I DON'T KNOW YET

Standard Quantity of Direct Materials × Standard Price of Direct Materials is the calculation to compute the Standard Cost of Direct Materials.

Standard Quantity of Direct Labor × Standard Price of Direct Labor is the calculation to compute the Standard Cost of Direct Labor.

Total estimated variable Manufacturing Overhead / Total estimated amount of the allocation base = Variable Manufacturing Overhead rate

Standard Quantity of Machine Hours × Variable Manufacturing Overhead rate = Standard Variable Manufacturing Overhead
Pilot Manufacturing prepared a report and noted budgeted fixed overhead costs of $3.25 per unit at 1,375 units. In October, the managerial accountant incurred actual fixed overhead costs of $4,600 and the actual production was 1,500 units.
What is Pilot Manufacturing’s fixed overhead budget variance for October?
ANSWER
INCORRECT
·         
$131.25 F
·         
$1,312.50 U
·         
YOU WERE SURE AND INCORRECT
$1,312.50 F
·         
THE CORRECT ANSWER
$131.25 U
·         
I DON'T KNOW YET
The fixed overhead budget variance for October is $131.25 U. The other answers are not correct.
Fixed Manufacturing Overhead Budget Variance = Actual Fixed Overhead Costs – Budgeted Fixed Overhead Costs
= $4,600 – ($3.25 × 1,375)
= $4,600 - $4,468.75 = $131.25 U
The variance is unfavorable because the actual fixed overhead costs exceed budgeted costs.


Which of the following best describes a disadvantage of standard costing which might occur when the production manager purchases a large quantity of raw materials which results in the production manager overproducing to obtain a favorable fixed overhead variance?
ANSWER
INCORRECT
·         
Outdated or inaccurate standards
·         
YOU WERE SURE AND INCORRECT
Focus on operational performance measures and visual management
·         
Lack of timeliness
·         
THE CORRECT ANSWER
Unintended behavioral consequence
·         
I DON'T KNOW YET

An unintended behavioral consequence is a disadvantage of standard costing which occurs occurs when the production manager purchases a large quantity of raw materials and results in the production manager overproducing to obtain a favorable fixed overhead variance.

An outdated or inaccurate standard is a disadvantage when costs become outdated or inaccurate during changes in the production process.

Lack of timeliness is a disadvantage when a manager fails to compute updated variance costs.

A focus on operational performance measures and visual management is a disadvantage when a manager fails to provide accurate data to promote operational standards and visual tools which might increase operational performance of front-line workers.

Pool Manufacturing reported the following information for April. What is Pilot Manufacturing’s fixed overhead volume variance for April?

Pool Manufacturing
Manufacturing Report for April
Number of parts produced
40,000 parts
Standard variable manufacturing overhead rate
$35 per machine hour
Standard hours required per part
0.20 machine hours
Actual machine hours
3,250 machine hours
Actual variable manufacturing overhead costs
$102,000

ANSWER
INCORRECT
·         
THE CORRECT ANSWER
$4,000 U
·         
$4,000 F
·         
YOU WERE SURE AND INCORRECT
$400 F
·         
$400 U
·         
I DON'T KNOW YET

Pilot Manufacturing’s fixed overhead volume variance for April is $4,000 U. The other answers are not correct.
Step 1: Compute Standard Fixed Overhead Cost Allocated to Production
= 40,000 parts × .20 machine hours × $35 per hour
= 8,000 machine hrs/part × $35/machine hr = $280,000
Step 2: Fixed Overhead Volume Variance = Budgeted Fixed Overhead – Standard Fixed Overhead Cost Allocated to Production
= $284,000 - $280,000 = $4,000 U


Marshall’s Toy Shop produces and sells small baseballs for children. During the production process, the producer uses twelve ounces of special glue for each baseball, including an allowance for normal amounts of spoilage and waste. The manager can purchase the glue for $.75 per ounce.
What is the standard cost of glue for each baseball?
ANSWER
INCORRECT
·         
$3.03
·         
THE CORRECT ANSWER
$3.00
·         
YOU WERE SURE AND INCORRECT
$3.30
·         
$.30
·         
I DON'T KNOW YET
The standard cost of glue for each baseball is $3.00/oz. The other answers are not correct.
4 oz. × $.75/oz. = $3.00


Pool Manufacturing manufactures parts for one type of pool. The managerial accountant provided the following data for April:

Pool Manufacturing
Manufacturing Report for April
Number of parts produced
40,000 parts
Standard variable manufacturing overhead rate
$35 per machine hour
Standard hours required per part
0.20 machine hours
Actual machine hours
3,250 machine hours
Actual variable manufacturing overhead costs
$102,000

What is the variable manufacturing overhead efficiency variance in April?
ANSWER
INCORRECT
·         
$28,000 F
·         
$280,000 U
·         
YOU WERE SURE AND INCORRECT
$28,000 U
·         
THE CORRECT ANSWER
$280,000 F
·         
I DON'T KNOW YET

The variable manufacturing overhead efficiency variance in March is $280,000 F. The other answers are not correct.
Variable Manufacturing Overhead Efficiency Variance = Standard Rate × Actual Hours × Standard Hours Allowed.
= $35 × [3,250 machine hours – (40,000 parts × 0.20 machine hours)]
= $35 × (3,250 machine hours -8,000)
= ($35 × 8,000) = $280,000 F
The variance is favorable since the standard machine hours exceeded the actual machine hours.

Standard Quantity of Direct Labor × Standard Price of Direct Labor is the calculation to compute ________.
ANSWER
INCORRECT
·         
the variable manufacturing overhead rate
·         
YOU WERE SURE AND INCORRECT
standard cost of direct materials
·         
standard variable manufacturing overhead
·         
THE CORRECT ANSWER
standard cost of direct labor
·         
I DON'T KNOW YET

Standard Quantity of Direct Labor × Standard Price of Direct Labor is the calculation to compute the standard cost of direct labor.

Total Estimated Variable Manufacturing Overhead / Total estimated amount of the allocation base = Variable Manufacturing Overhead Rate

Standard Quantity of Machine Hours × Variable Manufacturing Overhead Rate = Standard Variable Manufacturing Overhead

Standard Quantity of Direct Materials × Standard Price of Direct Materials is the calculation to compute the standard cost of direct materials.

Which of the following best describes an advantage of a costing system that occurs when a manager provides an employee with a reasonable or attainable goal?
ANSWER
INCORRECT
·         
Standard costing systems simplifying bookkeeping
·         
YOU WERE SURE AND INCORRECT
Cost benchmark
·         
Usefulness in budgeting
·         
THE CORRECT ANSWER
Motivation
·         
I DON'T KNOW YET

Motivation is an advantage of a costing system that occurs when a manager provides an employee with a reasonable or attainable goal.

Cost benchmark is an advantage of standard costing which results when updated standards produce valid benchmarks.

Usefulness in budgeting is an advantage of standard costing which occurs when standards are used as the basis for many components of the master budget.

Standard costing systems simplifying bookkeeping is an advantage of standard costing which results when Work in Process Inventory is recorded at standard cost instead of actual cost and variances between actual and standard costs are immediately captured in variance accounts on the general ledger.


Hillen Enterprises produces wheat and flour for the baking industry. The managerial accountant reported the following information at the end of the first quarter. What is the direct materials price variance? Is the direct materials price variance favorable or unfavorable?

Hillen Enterprises
Direct Materials Price Report
Quarter Ending March 31
Direct materials standard (10 lbs. per unit @$0.75/lb.)
$7.50 per finished good
Actual direct materials purchased
$40,000 pounds
Actual Direct Materials Used (AQU)
37,000 pounds
Actual Price (AP) paid per pound
$0.85

ANSWER
INCORRECT
·         
THE CORRECT ANSWER
$4,000 unfavorable
·         
$400 favorable
·         
YOU WERE SURE AND INCORRECT
$4,000 favorable
·         
$400 unfavorable
·         
I DON'T KNOW YET

The direct materials price variance is $4,000 unfavorable.

AQP × (AP – SP)
40,000 × ($0.85 - $0.75) = 40,000 × $0.10 = $4,000 unfavorable
The actual direct material cost per pound was more than the standard direct material cost per pound, so the variance is unfavorable. The other answers are not correct.

Actual Hours × (Actual Rate – Standard Rate) is the formula to compute the ________.
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
direct labor rate variance
·         
direct labor efficiency variance
·         
YOU WERE SURE AND INCORRECT
direct material quantity variance
·         
direct material price variance
·         
I DON'T KNOW YET

Actual Hours × (Actual Rate – Standard Rate) is the formula to compute the direct labor rate variance.

Standard Rate × (Actual Hours – Standard Hours Allowed) is the formula to compute the direct labor efficiency variance.

Actual Quantity Purchased × (Actual Price – Standard Price) is the formula to compute the direct material price variance.

Standard Price × (Actual Quantity Used – Standard Quantity Allowed) is the formula to compute the direct material quantity variance.


Total estimated variable Manufacturing Overhead / Total estimated amount of the allocation base is the calculation to compute the ________.
ANSWER
INCORRECT
·         
Standard Fixed Manufacturing Overhead
·         
standard cost of variable manufacturing overhead
·         
YOU WERE SURE AND INCORRECT
Fixed Manufacturing Overhead Rate
·         
THE CORRECT ANSWER
Variable Manufacturing Overhead Rate
·         
I DON'T KNOW YET

Total estimated variable Manufacturing Overhead / Total estimated amount of the allocation base is the calculation to compute the Variable Manufacturing Overhead rate.

Standard Quantity of Machine Hours × Variable Manufacturing Overhead rate = Standard Variable Manufacturing Overhead = Standard cost of variable manufacturing overhead

Total Estimated Fixed Manufacturing Overhead / Total estimated amount of the allocation base = Fixed Manufacturing Overhead Rate

Standard Quantity of Machine Hours × Fixed Manufacturing Overhead rate = Standard Fixed Manufacturing Overhead


Pool Manufacturing manufactures parts for one type of pool. The managerial accountant provided the following data for April:

Pool Manufacturing
Manufacturing Report for April
Number of parts produced
40,000 parts
Standard variable manufacturing overhead rate
35 per machine hour
Standard hours required per part
0.20 machine hours
Actual machine hours
3,250 machine hours
Actual variable manufacturing overhead costs
$102,000

What are the actual costs in April associated with the manufacturing the pool parts?
ANSWER
INCORRECT
·         
$10,198.50
·         
YOU WERE SURE AND INCORRECT
$100,198.50
·         
$1,019.85
·         
THE CORRECT ANSWER
$101,985
·         
I DON'T KNOW YET

The actual costs in April associated with the manufacturing the pool parts = $101,985.
First, compute the actual rate: Actual Rate = $102,000 / 3,250 = $31.38.
Next, compute the actual cost: Actual Hours × Actual Rate = 3,250 machine hours × $31.38 = $101,985. The other answers are not correct.

Which of the following is the formula to compute the direct labor rate variance?
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
Actual Hours × (Actual Rate – Standard Rate)
·         
YOU WERE SURE AND INCORRECT
Actual Quantity Purchased × (Actual Price – Standard Price)
·         
Standard Rate × (Actual Hours – Standard Hours Allowed)
·         
Standard Price × (Actual Quantity Used – Standard Quantity Allowed)
·         
I DON'T KNOW YET


The formula to compute the direct labor rate variance is Actual Hours × (Actual Rate – Standard Rate).

The formula to compute the direct labor efficiency variance is Standard Rate × (Actual Hours – Standard Hours Allowed).

The formula to compute the direct material price variance is Actual Quantity Purchased × (Actual Price – Standard Price).

The formula to compute the direct material quantity variance is Standard Price × (Actual Quantity Used – Standard Quantity Allowed).


Pool Manufacturing manufactures parts for one type of pool. The managerial accountant provided the following data for March:

Pool Manufacturing
Manufacturing Report for March
Number of parts produced
35,000 parts
Standard variable manufacturing overhead rate
30 per machine hour
Standard hours required per part
0.20 machine hours
Actual machine hours
3,250 machine hours
Actual variable manufacturing overhead costs
$92,000

What are the actual costs in March associated with the manufacturing the pool parts?
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
$92,007.50
·         
$920,075
·         
$9,2007.50
·         
YOU WERE SURE AND INCORRECT
$9,200.70
·         
I DON'T KNOW YET

The actual costs associated with the manufacturing the pool parts = $92,007.50.
First, compute the actual rate: Actual Rate = $92,000 / 3,250 = $28.31.
Next, compute the actual cost: Actual Hours × Actual Rate = 3,250 machine hours × $28.31 = $92,007.50. The other answers are not correct.


The unintended behavioral consequence, a disadvantage of standard costing, occurs when ________.
ANSWER
INCORRECT
·         
costs become outdated or inaccurate during changes in the production process
·         
a manager fails to compute updated variance costs
·         
YOU WERE SURE AND INCORRECT
a manager fails to provide accurate data to promote operational standards and visual tools which might increase operational performance of front-line workers
·         
THE CORRECT ANSWER
the production manager purchases a large quantity of raw materials which results in the production manager overproducing to obtain a favorable fixed overhead variance
·         
I DON'T KNOW YET


The unintended behavioral consequence is a disadvantage of standard costing which occurs when the use of traditional standards produce unintended behavioral results. This could include a situation where a production manager purchases a large quantity of raw materials which results in the production manager overproducing to obtain a favorable fixed overhead variance.

An outdated or inaccurate standard is a disadvantage when costs become outdated or inaccurate during changes in the production process.

Lack of timeliness is a disadvantage when a manager fails to compute updated variance costs.

A focus on operational performance measures and visual management is a disadvantage when a manager fails to provide accurate data to promote operational standards and visual tools, which might increase operational performance of front-line workers.

Marty’s Motors produces metal for parts in the automotive industry. The managerial accountant reported the following information at the end of the second quarter. What is the direct materials price variance? Is the direct materials price variance favorable or unfavorable?

Marty’s Motors
Direct Materials Price Report
Quarter Ending June
Direct materials standard (9 lbs. per unit @$0.85/lb.)
$7.65 per finished good
Actual direct materials purchased
50,000 pounds
Actual Direct Materials Used (AQU)
47,000 pounds
Actual Price (AP) paid per pound
$0.90

ANSWER
INCORRECT
·         
$250 unfavorable
·         
$250 favorable
·         
YOU WERE SURE AND INCORRECT
$2,500 favorable
·         
THE CORRECT ANSWER
$2,500 unfavorable
·         
I DON'T KNOW YET
The direct materials price variance is $2,500 unfavorable.

AQP × (AP – SP)
50,000 × ($0.90 - $0.85) = 50,000 × $0.05 = $2,500 unfavorable
The actual direct material cost per pound was less than the standard direct material cost per pound the variance is favorable, otherwise unfavorable. The other answers are not correct.


The variable overhead rate variance ________ .
ANSWER
INCORRECT
·         
is directly tied to the efficiency with which the machine hours are used
·         
THE CORRECT ANSWER
is the difference between the actual variable manufacturing overhead costs incurred during the period and the amount of variable manufacturing overhead expected, considering the number of actual hours worked
·         
YOU WERE SURE AND INCORRECT
is the difference between the actual machine hours run and the standard machine hours allowed for the actual volume, computed at the variable manufacturing overhead rate
·         
is NOT known as the variable overhead spending variance
·         
I DON'T KNOW YET
The variable overhead rate variance is the difference between the actual variable manufacturing overhead costs incurred during the period and the amount of variable manufacturing overhead expected, considering the number of actual hours worked is true.

The variable overhead efficiency variance is the difference between the actual machine hours run and the standard machine hours allowed for the actual volume, computed at the variable manufacturing overhead rate.

The variable overhead efficiency variance is directly tied to the efficiency with which the machine hours are used instead of the variable overhead rate variance.

The variable overhead rate variance is known as the variable overhead spending variance.


Which of the following is the formula to compute the direct labor efficiency variance?
ANSWER
INCORRECT
·         
Actual Quantity Purchased × (Actual Price – Standard Price)
·         
YOU WERE SURE AND INCORRECT
Standard Price × (Actual Quantity Used – Standard Quantity Allowed)
·         
Actual Hours × (Actual Rate – Standard Rate)
·         
THE CORRECT ANSWER
Standard Rate × (Actual Hours – Standard Hours Allowed)
·         
I DON'T KNOW YET

Standard Rate × (Actual Hours – Standard Hours Allowed) is the formula to compute the direct labor efficiency variance.

Actual Hours × (Actual Rate – Standard Rate) is the formula to compute the direct labor rate variance.

Actual Quantity Purchased × (Actual Price – Standard Price) is the formula to compute the direct material price variance.

Standard Price × (Actual Quantity Used – Standard Quantity Allowed) is the formula to compute the direct material quantity variance.
Which of the following is NOT true about the variable overhead rate variance?
ANSWER
INCORRECT
·         
THE CORRECT ANSWER
The variable overhead rate variance is directly tied to the efficiency with which the machine hours are used instead of the variable overhead rate variance.
·         
YOU WERE SURE AND INCORRECT
The variable overhead rate variance is the difference between the actual variable manufacturing overhead costs incurred during the period and the amount of variable manufacturing overhead expected, considering the number of actual hours worked.
·         
The variable overhead rate variance is known as the variable overhead spending variance.
·         
Variable manufacturing overhead is made up of a number of various costs, including indirect materials, indirect labor, or other variable overhead costs.
·         
I DON'T KNOW YET
The variable overhead rate variance is directly tied to the efficiency with which the machine hours are used instead of the variable overhead rate variance is NOT a true statement. The variable overhead efficiency variance is directly tied to the efficiency with which the machine hours are used instead of the variable overhead rate variance. The other answers are true statements about the variable overhead rate variance.



No comments:

Post a Comment